PROJECTS
Mmapeu House
Mmapeu House project involved the construction of a 600m2 upmarket residential unit located on a site with a steep terrain in the north east of Johannesburg. Innovative construction methods were required to deal with the challenges posed by the steep terrain, limited access and adherence to strict estate regulations.
Value to Client: Construction required significant cut and fill operations within a confined space which posed challenges with regards to adherence to Occupational Health and Safety Compliance. In addition, a complex foundation systems was required as well as specialized solutions for drainage and stormwater management. Prana had to meticulously manage the additional labor and materials needed to ensure the delivery of a good quality product within the allocated time frame.
Project Details:
Date: 2018 – 2019
Client: Novation Engineering
Project Type: Construction
Project Value: R5.1 (million)
Contractor: Prana Consulting
National Road R524
Prana Consulting was appointed as a Targeted Enterprise partner for the upgrade on National Road R524. The aim of the project is to relieve congestion to acceptable levels of service, improve road safety and ensure adequate pavement capacity for a minimum design period of 20 years. The cope of works includes project assessment, design development and tender documentation, as well as investigations required for design development.
Project Details:
Date: 2018 – 2020
Client: SANRAL
Project Type: Civil Engineering
Project Value: R492 476 000 (million)
Contractor: Prana Consulting as Targeted Enterprise
Katlehong Swimming Pool
Katlehong Swimming pool site is a communal swimming facility constructed for the community of Katlehong Township. Due to the many sinkhole formation events that have occurred on site over time, the facilities have never being used by the beneficiary community. Several investigations were conducted in the past to determine the site’s dolomite stability for the continued use of the facilities.
Prana was appointed to re-assess the site’s dolomite stability with particular regards to determining possible remedial measures and solutions that could minimize the risk of occurrence of further dolomite related instabilities. The objective of the investigation was to establish if the communal facilities can be rehabilitated for safe utilization considering the capital investment and scarcity of suitable land for similar facilities within ease of reach by the community of the surrounding Katlehong Township residents.
A comprehensive investigation is being conducted including trench excavations and profiling, gravity survey, foundations inspections, crack survey, DPSH testing, leak detection, pressure tests of the site’s wet services network; as well as further borehole drilling and 3D modelling of boreholes from current and past drilling programmes.
Value to Client:Restoring the facilities to a safe and functioning condition will ensure that value is realized in the amount spent thus far by government on constructing and upgrading the facilities. The community benefit will include accessibility, exposure to swimming as a professional sport and for recreation and improving the morale of community.
Project Details:
Date: 2018 – 2019
Client: City of Ekurhuleni
Project Type: Structural Integrity Assessment
Project Value: R1.6 (million)
Contractor: Prana Consulting
Labore Industrial Park Road Network Upgrade
The objective of the project is to upgrade the Labore Roads Network by completing the design and construction of roads that were partially constructed and also to upgrade the existing gravel roads to surfaced roads. The project involved the design, documentation and procurement and construction management of the roads. Technical challenges encountered included restricted road reserves which were inadequate for the type of traffic, expedited project timelines which were met without compromising on quality and cost. During construction phase the challenges included budget constraints by the Client and balancing Client needs with community expectations.
Value to Client: Labore Industrial Park has been identified by City of Ekurhuleni as one of several Strategic Land Parcels (SLP’s). The incomplete infrastructure was a deterrent for investors and the upgrade will attract investments to the industrial park and will fast track development and advance City of Ekurhuleni’s Economic development agenda. The upgrade of Boland Road will alleviate traffic congestion from Geluksdal Road which is the currently the only access road from the R23 to Tsakane Township.
Project Details:
Date: 2018 – 2019
Client: City of Ekurhuleni
Project Type: Roads & Stormwater
Project Value: R49 (million)
Contractor: Prana Consulting
LIST OF PROJECTS